Prince George Update May 01, 2008
- Follow up with First Nations Bands and Prince George District Liaison Officer on Consultation process and information sharing. This include very successful meeting on May 8, 2008
- Working on capacity building with local First Nation Band
- Engaged with finalizing Planting blocks layout, GPS and mapping on impacted openings by MPB (including some field data collection of ecological and soils information and developing Work Plans)
- Engaged with recce surveys on previously identified openings impacted by MPB – 15,000 ha
- Engaged with prescription development for 2009/2010 on impacted openings by MPB – Net Down from 15,000 ha
- A tender request will be issue for Summer Tree Planting 2008 in local newspaper and in FIRS/PINES advertising webpage by May 15, 2008
- A tender request will be issue for Full Surveys 2008 in local newspaper and in FIRS/PINES advertising webpage by end of May.
- Direct award will be issue to local First Nation Band for Danger Tree Assessment and Falling
- Filter down and adjusting GIS information footprint from NSR and Impeded projects in Prince George District on openings affected by MPB and scheduled for Forest Health Surveys.
- GIS adjustment for road inventory and responsibility in Prince George District.
|
100 Mile House
|
TFL 1
|